| DoTS/DPS Scheduled Changes | ||||||||||||||
| Report run on: | August 23, 2005 7:59 AM | |||||||||||||
| Scheduled | Change Name | User Impact | ||||||||||||
| 27-JUN-05 | LAWS - Lawson 8.1 upgrade | upgrade to 8.1 apps, ESS, MSS and refit to time and attendance. There will be a navigation change for ESS and MSS. Other, all other changes are business process related to payroll, some major programs broken down into 2. | ||||||||||||
| 27-AUG-05 | SHPT - Move of Sharepoint cluster | The SharePoint cluster will be moved from one rack to another in the computer room | ||||||||||||
| 25-AUG-05 | DTWH - Promote Data Vault Hub Codes project to production (DVPROD) | This project provides the change data capture for all code tables in the ODS. | ||||||||||||
| 22-AUG-05 | GIS_ - Process to update the streetfile that mapservices points to | A scheduled task will be added to dpsgis02 (production) and dpsgis03 (development) to copy the newest street file over and to refresh the services. The task will take place on Monday evenings after the changes from Routing and PAR have been added to the street file. | ||||||||||||
| 25-AUG-05 | GIS_ - Change MapServices to point to merged walkzone layers | MapServices currently points to a different layer for every middle and high school walkzones. The walkzones have been merged to a single layer for middle and a single layer for high school walkzones. MapServices will point to the new merged layers which will increase efficiency and assist in keeping SDE clean. | ||||||||||||
| 25-AUG-05 | NETW - Comcast fiber move 8/25/05 | Comcast are going to do a fiber conversion on the 288 count between TCC and TCS-43. The city has there I-net backbone on this and the city channel 8 from the city and county building. DPS is also on this fiber for there I-net so they need to be contacted. This will happen on the morning of the 25th of August and should only last an hour. This should be back up around 1:00 am. | ||||||||||||
| 26-AUG-05 | NETW - Comcast cable move 8/26/05 | Comcast is replacing the fiber we used for the underground conversion installed earlier this month on 16th & Milwaukee since this fiber run is short this will be done around 2:00 am and will take only about an hour to do this work on the morning of the 26th of August. Comcast cannot change the timing of this project. I realize that school will have just begun at that point but given the timing and short duration, hopefully this should not cause a significant issue for you all. | ||||||||||||
| Page 1 | ||||||||||||||
| DoTS/DPS Scheduled Changes | ||||||||||||||
| Report run on: | August 23, 2005 7:59 AM | |||||||||||||
| Scheduled | Change Name | User Impact | ||||||||||||
| 27-AUG-05 | IC__ - Campus Upgrade 2006.2 | The Campus 2006.2 upgrade consists of product enhancements and product fixes since the last product update on July 11, 2005. The enhancements are composed of requested product functionality from local Districts moving to Infinite Campus. The product fixes are completion of submitted work orders to IC customer support. | ||||||||||||
| 25-AUG-05 | DTWH - Promote STUDENT_PROFILE_FROM_IC project to production (ODSPROD) | This project will use the IC data as the source for student information included in the Student profile report. The IC data will refresh the ODS and subsequently the Student Profile report on a weekly basis. The data now available for the Student profile report is student demographic information, current & historical enrollment data, student schedules, incident/outcome data, program svcs & transcript info. It includes31 ETL mappings, pulling data from 21 IC tables populatng 23 ODS tables. | ||||||||||||
| 19-AUG-05 | LAWS - Lawson to LION Interface | LION Extract File. DH220 creates extract file for LION (Library).This file has all the employees details like DPDID,address,Last name,Firstname etc. New fields were added into the Extract file. Email Id and Classroom Field "STAFF". The Classroom Field will be used to seperate STAFF overdue notices from STUDENT overdue notices. The DPSID (without the 27137 prefix) was included in the UNIV ID (u) field | ||||||||||||
| 27-AUG-05 | EMAL - webmail move | Brief outage to allow webmail web cluster to be moved to a new rack. | ||||||||||||
| 22-AUG-05 | LAWS - Modified Script on DH290 | The Program DH290 sends a report to TALX company for unemployment. The problem was that the file was not being encrypted and FTPed automatically by the program. After making changes to the script, it works now. | ||||||||||||
| 22-AUG-05 | LAWS - Added Reason Codes to DH716 | In the program DH716, new reason codes were added .This screen checks for the teachers who are not eligible for transfer. | ||||||||||||
| 11-SEP-05 | EMC2 - SAN Upgrade | Upgrading SAN switch environment to Enterprise Class switches. If we are unable to do the upgrade on Aug 28th, the backup date is the weekend of September 10- 11. | ||||||||||||
| Page 2 | ||||||||||||||
| DoTS/DPS Scheduled Changes | ||||||||||||||
| Report run on: | August 23, 2005 7:59 AM | |||||||||||||
| Scheduled | Change Name | User Impact | ||||||||||||
| 25-AUG-05 | DTWH - Promote PAR_QUERY_VIEWS project to production (ODSPROD) | Create new views to allow PAR access to ODS data. Alter user to allow view creation (i.e., grant resource and quota). This is the first implementation of the new virtual data mart model for accessing the ODS | ||||||||||||
| Page 3 | ||||||||||||||